# Lathrop approves $25.9 million plan to replace Manthey Road Bridge
- URL: https://www.onsiteobserver.com/lathrop-approves-25-9-million-plan-to-replace-manthey-road-bridge/
- Published: 2026-11-25T00:48:46.000Z
- Updated: 2026-11-25T00:48:46.000Z
- Author: Vitaliy Moskalenko
- Tags: Infrastructure

The Manthey Road Bridge was nearly 90 years old when Lathrop residents gathered at the senior center in November 2014 to see three options for replacing it. Even then, they wanted to know when construction would begin. By the time the City Council approved its replacement on Nov. 9, the steel span over the San Joaquin River was 100\. Assistant City Manager Michael King’s timeline called for the city to seek construction bids in October 2027\. It did not say when crews would begin work.

The city estimates the project will cost $25.9 million. It would move the crossing about a third of a mile downstream, connecting Golden Valley Parkway in Mossdale Village to Stewart Road in River Islands. Before the vote, Vice Mayor Jennifer Torres-O’Callaghan said she knew residents would ask about the time it had taken to get this far.

“So is 12 years standard for Caltrans?” she asked.

Mayor Paul Akinjo put the question to City Manager Stephen Salvatore. “These are the questions we are getting every time,” Akinjo said. “Why does it take so long to get a project from paper to delivery?”

“I’ll answer the question as diplomatically as I can,” Salvatore began. He said requirements can change while a project is under review, leaving work to be “evaluated and reevaluated and reevaluated until you’re nauseated to death.”

The bridge’s consultants described one such delay in a [2024 report](https://www.ci.lathrop.ca.us/sites/default/files/fileattachments/city%5Fcouncil/meeting/27100/2024-09-09%5Fitem%5F4.13%5Fapprove%5Famendment%5Fno.%5F5%5Fwith%5Fwsp%5Fusa%5Finc.%5Ffor%5Fthe%5Fmanthey%5Frd%5Fbridge%5Freplacement%5Fproj%5Fcip%5Fps%5F12-04.pdf?utm%5Fsource=chatgpt.com) to the city. A Caltrans district office had asked them for a plan to handle archaeological discoveries during construction. The agency’s cultural studies office then required a different plan and a separate agreement. After several rounds of revisions, Caltrans asked the consultants to update the original plan. By then, the consultants said, they had also had to update parts of the wildlife study several times.

Lathrop’s plans to replace the bridge date to 2012, and consultants began work two years later. The city’s [2020 draft environmental study](https://files.ceqanet.lci.ca.gov/264572-2/attachment/CbTbAx-hn8irkUzwVPtenYgS5KCFZJnfT1KNXwBHK7jOZ9%5FdfL-tFfgzHs99npxpQp2kLksuIqUa%5FLTM0?utm%5Fsource=chatgpt.com) projected that the new bridge would open to traffic in fall 2023\. In 2021, the city sought public comment again after revising protections for the riparian brush rabbit and Swainson’s hawk.

Lathrop led the state environmental review. Caltrans led the federal review and signed a finding of no significant impact on Oct. 6\. On Nov. 9, the council adopted the city’s environmental study, made its mitigation measures conditions of approval and adopted a plan to monitor compliance.

The city expects to pay for the replacement with federal Highway Bridge Program funds and local development fees. “We have the money, right? But we don’t have the permits and the clearance to do anything,” Akinjo said. The staff report confirmed the city had set aside enough for the environmental phase. A construction contract and any required funding agreements would come back to the council separately.

Victoria “Torie” Cortez, a Lathrop parent who had raised concerns about traffic near schools at a May council meeting, spoke during public comment. “Why is our neighbor, Manteca, able to get projects built so quickly?” she asked.

Cortez also wanted the council to address what would happen once the bridge opened. She said it would send more drivers looking for a shortcut onto streets around Mossdale Elementary School, including Autumn Rain Drive and Crescent Moon Way. She asked the council to make approval conditional on installing speed cushions and signs directing through traffic away from the neighborhood before construction begins. The council approved the project as presented.

Drivers would continue to use the old bridge while crews build its replacement. In 2012, Caltrans classified it as structurally deficient and functionally obsolete and gave it a sufficiency rating of 7.1 out of 100\. King told the council the bridge remains safe for drivers. He attributed much of the low score to narrow lanes, inadequate shoulders and limited access for cyclists and pedestrians. 

The new bridge would stretch about 532 feet, with one lane in each direction, 8-foot shoulders and sidewalks on both sides. Once it opens, crews would remove the old road bridge. The separate pedestrian bridge would stay, along with access to Mossdale Crossing Regional Park and its boat launch.

![The blue line traces the route of the new San Joaquin River crossing from Golden Valley Parkway in Mossdale Village to Stewart Road in River Islands, about a third of a mile downstream from the existing Manthey Road Bridge.](https://storage.ghost.io/c/e3/2f/e32feaaf-a1ce-486f-8068-a9b0cc9d6e12/content/images/2026/11/Manthey-Bridge-Build-Alternative.jpg)

The blue line traces the route of the new San Joaquin River crossing from Golden Valley Parkway in Mossdale Village to Stewart Road in River Islands, about a third of a mile downstream from the existing Manthey Road Bridge. Image: City of Lathrop.

In April 2025, Public Works Director Brad Taylor told the Planning Commission he anticipated [construction by 2027](https://www.ci.lathrop.ca.us/sites/default/files/fileattachments/planning%5Fcommission/meeting/27862/pc%5Fminutes%5F4-16-25%5Fregular.pdf?ref=onsiteobserver.com#page=3). King told the council on Nov. 9 he expects work to move faster after environmental review. The city still has to finish the design, acquire land and put construction out to bid.